Ă۶ąĘÓƵ

Understand project timelines

What you’ll learn:

  • Get an overview of project planning and management using Workfront. Learn how parent tasks group several sub-tasks, which are assigned to job roles and later to users with the necessary skills. Predecessors indicate sequential relationships between tasks, while tasks without predecessors can be done in parallel. The Gantt chart offers a visual timeline, and the Critical Path feature highlights tasks that could delay the project if they slip.
  • Different views in Workfront, such as the standard view for planning and the status view for monitoring progress, which includes flags for progress, comments, documents, issues, approvals, critical path, and milestones. Recent activity can be tracked to see updates and notes.
  • Scheduling can be done from a start date or a completion date, with Workfront calculating the corresponding dates based on task durations and predecessors. The video advises scheduling from a start date for critical completion dates to allow some slack. Task constraints, such as “as soon as possible” and “as late as possible,” are also covered, showing how they affect task scheduling. Custom views can be created to display task constraints.

video poster

Transcript

Here we have a project in the process of being planned. Parent tasks are not usually assigned to a person when they are used to group several tasks, like here in Create, Copy, and Layout. Each sub-task has a job role assigned to it, and will later be assigned to a user who has the needed skill. When the work done in one task is required as input to another task, predecessors are used to show this sequential relationship. When two tasks or parent tasks can be done in parallel, no predecessor is used. This is the case with Photo Shoot. Create, Copy, and Layout does not have to even be started before Photo Shoot can start. You can see this by looking at the start on dates of both tasks. They are the same. A good way to get an overview of your timeline is with the Gantt chart. Clicking here will show both the Gantt chart and the task view together. Here it’s a little more obvious that the Photo Shoot subtasks are independent of other subtasks. You can collapse tasks in the task view to improve the overview. You can turn on Critical Path to see the critical path in your project. To do this, click on the gears icon. If any task on the critical path slips, the planned completion date for the project slips. Photo Shoot would have to slip a lot before it becomes part of the critical path.

We’re using the standard view right now, which is good for creating your project plan. When you’re monitoring your plan, you might want to use the status view, which shows you a status column and a flags column. The flags give you a quick look at several interesting points for each task. Hover over a flag to see what it shows. The first flag shows the progress status.

The next shows notes or comments made on the task. Click on it to add a comment or read a comment.

If there are any notes on the task, the flag will indicate it by not being grayed out. Next is a document flag. If there are any documents attached to this task, it will not be grayed out, and you can click on it to go to the documents area for this task. Next is open issues. There may be issues on this task that have already been resolved. Resolved issues will not turn this flag on. But if there are any unresolved or open issues, then the flag will indicate it. Again, clicking here will take you to the issues tab. If the approval flag is grayed out, there is no approval required for this task. If it is lit, then there is an approval required. The next flag is on if this task is on the critical path, and off if it’s not. The diamond flag appears if the task is a milestone, and hovering over it will tell you the name of the milestone. Recent activity is another useful view.

It shows the last update date and the last note, along with the name of who made the last update. Should you schedule your project from a start date or a completion date? You can set this in project details. When you create a project, you have the option to choose the schedule mode. If you choose start date, you’ll enter the planned start date here. Then Workfront will calculate the planned completion date based on the task durations and predecessors in your project. If you choose completion date, you’ll enter the planned completion date here. Then Workfront will calculate the planned start date based on the task durations and predecessors in your project. A common misconception is that you should choose to schedule from a completion date if you need your project to finish by a particular date. This is not true. Either schedule mode will help you work toward the planned completion date. Scheduling from a completion date simply means you tell Workfront your desired completion date, and it will calculate the latest possible date that you can start and still get it done according to your plan. If one task on your critical path slips by a day, you’ll miss your planned completion date by a day. If your completion date is critical, it’s best to schedule from a start date, where your planned completion date calculates to a little before the particular date you need to be done. Then you have a little slack in your timeline in case something takes longer than expected. Back to our tasks now. There’s another thing that Workfront does that you need to know about. It’s something called a task constraint that each task has. We can change to a task constraint view to see this. In this view, you can see the task constraints. There are 11 of them. For now, we’re only concerned about two task constraints, as soon as possible and as late as possible. When you choose to schedule from a start date, which is what we have now, Workfront sets the default task constraint for each new task created to as soon as possible. But if you choose to schedule by a completion date, Workfront sets the default task constraint for each new task created to as late as possible. This is important to be aware of if you ever change the schedule mode after you’ve created your project. You can see the difference it makes in the calculated plan dates for task 11 when I change the task constraint to as late as possible. The planned completion date changes from December 27th to January 27th. This is because task 11 was not on the critical path, and the schedule mode is set back to start date. But as you can see now in the Gantt chart, it’s been moved up to complete as late as possible without changing the planned completion date of the project. If you want to see a task constraint column like this, you can create a custom view. This is all there is to it. Go to the View tab and select New View. Then click on Add Column. Start typing constraint. And select Task Constraint under the task object. Name the view and click Save View.

IMPORTANT
For a more complete explanation of duration types and task constraints see Understand and manage duration types and task constraints.

Key takeaways

  • Task Management and Assignment: Parent tasks group several sub-tasks, which are assigned to job roles and later to users with the necessary skills. ​ Predecessors indicate sequential relationships, while tasks without predecessors can be done in parallel. ​
  • Gantt Chart and Critical Path: The Gantt chart provides a visual timeline of the project, and the Critical Path feature highlights tasks that could delay the project if they slip. ​
  • Views and Monitoring: Different views in Workfront, such as the standard view for planning and the status view for monitoring, include flags for progress, comments, documents, issues, approvals, critical path, and milestones. Recent activity can also be tracked. ​
  • Scheduling Options: Projects can be scheduled from a start date or a completion date, with Workfront calculating the corresponding dates based on task durations and predecessors. ​ Scheduling from a start date is recommended for critical completion dates to allow some slack. ​
  • Task Constraints: Task constraints like “as soon as possible” and “as late as possible” affect task scheduling. ​ Changing the schedule mode after project creation can impact task constraints and planned dates. ​ Custom views can be created to display task constraints. ​

To change or not to change dates on your ​project timelines…

PROS (Changing dates)
CONS (Changing dates)
PROS (Not changing dates)
CONS (Not changing dates)
  • Reduce stress/provide up-to-date expectations for users - “Creatives wouldn’t know what’s real”
  • Accurate resource allocation, especially in the Workload Balancer
  • Use journal entry reports (or project duration) to call out date changes
  • Use of condition to show if project is out of scope
  • Can add a custom form (or use issues) to track changes– why it was pushed, by whom, how long
  • Misleading data as reports do not reflect true state
  • False perception of progress - illusion that everything is on track​
  • Foster a culture of always pushing back timelines instead of addressing root causes​
  • Loss of stakeholder confidence / team perception to meet deadlines
  • Accurate representation of project timeline – data can be used for analysis and to tell a clear story of what happened
  • Option to change duration or add lag to predecessor instead
  • Easily identify process improvements for future project planning/ risk mngt​
  • Option to leverage baselines to capture original project plan and use that as comparison
  • If you don’t have the people to do it, and to do it for everything, don’t do it​
  • User confusion and/or frustration - abundance of “late” tasks despite the fact that they just got notified
  • Resources were effectively allocated to map to the original plan, but now are overloaded with delayed work
  • Project timeline cannot be used to clearly communicate updates to stakeholders
recommendation-more-help
c9fbcf61-6d19-481e-a9ab-f54a0ae0ee8a