ÃÛ¶¹ÊÓƵ

Overview of goal progress and condition in ÃÛ¶¹ÊÓƵ Workfront Goals

Your organization must have the following to use the functionality described in this article:

  • For the new plan and license structure:

    • An Ultimate plan

      Or

      An additional license for ÃÛ¶¹ÊÓƵ Workfront Goals for the Prime or Select ÃÛ¶¹ÊÓƵ Workfront plans. For information, see .

  • For the current plan and license structure:

    • A Pro or higher
    • An ÃÛ¶¹ÊÓƵ Workfront Goals license in addition to a Workfront license.

Contact your Workfront account manager to learn about a Workfront Goals license.

For additional information about access to Workfront Goals, see Requirements to use Workfront Goals.

ÃÛ¶¹ÊÓƵ Workfront calculates goal progress automatically, based on the progress of its progress indicators.

Overview of goal progress and threshold

After you activate a goal, Workfront Goals starts calculating its progress and condition and displays the following indicators when you hover over the Progress field:

Indicator
Indicator description
Actual percent complete
How much of the goal has actually been completed so far. Workfront Goals calculates this value by averaging the percent complete of all progress indicators associated with the goal.
Expected percent complete
How much of the goal should be completed so far in order for the goal to complete on time. Workfront Goals calculates this value by looking at the Duration of the goal and the current moment in time. The goal should display this value at the current time, if it were to complete on time.
Progress
A label that indicates whether the goal is on target to be completed on time, or if it is at risk or in trouble of not completing.

Actual percent complete actual-percent-complete

Workfront Goals automatically calculates the actual percent complete of a goal based on the percent complete average of the goal progress indicators.

The following items are considered progress indicators for goals:

Expected percent complete expected-percent-complete

Workfront Goals automatically calculates the expected percent complete of a goal based on the total number of days in the duration of the goal as well as on the number of days that have passed since the goal start date.

Workfront Goals calculates the expected percent complete using the following formula:

Expected percent complete of goal = Number of days since the goal start date * 100/ Number of days in the goal duration

For example, if a goal is due to complete in 90 days, and today is the 45th day of that duration, then the Expected percent complete is 50%.

Progress and condition progress

Workfront Goals calculates a progress percentage and assigns a progress label to goals, based on what percentage from the Expected percent complete has been achieved at the current moment in time. The color of the goal percent complete bar changes to indicate the progress of the goal.

The goal’s Condition is also updated, accordingly, to indicate whether the goal is on target to complete on time, or it’s lagging behind.

Workfront Goals calculates the progress percentage of a goal using the following formula:

Goal progress percentage = Actual percent complete * 100 / Expected percent complete

For example, if the Expected percent complete is 53% at the current time and the Actual percent complete is 30%, the Goal progress percent complete is 56%. Workfront Goals labels this goal with a Condition of “In Trouble.â€

The following chart illustrates the relationship between the condition labels and the progress percentage:

The table below lists the goal condition labels and the goal progress percentages associated with each label.

TIP
Goal condition labels match Workfront project Condition name and color.
Goal progress name
Goal progress definition
Goal progress percentage
Color of percent complete bar
Condition indicator icon
New

The goal is newly created and it is not recording progress yet. A goal progress displays as New until someone updates its progress for the first time.

For information about updating goal progress, see Update goal progress in ÃÛ¶¹ÊÓƵ Workfront Goals.

No percentage
No bar
new_goal_icon_condition.png
On Target
The goal is performing as expected and there is a great likelihood that it will complete on time.
90-100%
Green
on_target_icon_condition.png
At Risk
The goal is lagging but it might still be possible to complete it on time.
70-89.99%
Yellow
at_risk_icon_condition.png
In Trouble
It is very likely that the goal will not complete on time.
0-69.99%
Red
in_trouble_icon_condition.png
recommendation-more-help
5f00cc6b-2202-40d6-bcd0-3ee0c2316b43