Set the project Planned Completion Date
The Planned Completion Date of a project is the date the project is set to complete.
The Planned Start and the Planned Completion Dates of a project rely on the dates of the tasks on the project. This article describes how you can manually or automatically set the Planned Completion Date of a project. For more information about the Planned Completion Date of a task, see Overview of the task Planned Completion Date.
The Planned Completion Date of a project can be set manually or automatically, depending on whether you schedule the project from the Start or from the Completion Date.
Access requirements
You must have the following access to perform the steps in this article:
table 0-row-2 1-row-2 2-row-2 3-row-2 layout-auto html-authored no-header | |
---|---|
ÃÛ¶¹ÊÓÆµ Workfront plan | Any |
ÃÛ¶¹ÊÓÆµ Workfront license |
New: Standard Or Current: Plan |
Access level configurations |
Edit access to Projects NOTE If you still don’t have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can modify your access level, see Create or modify custom access levels. |
Object permissions |
Manage permissions to the project For information on requesting additional access, see Request access to objects. |
For more detail about the information in this table, see Access requirements in Workfront documentation.
Manually set the Planned Completion Date of a project
You must manually set the Planned Completion Date of a project when you schedule the project from Completion Date.
To schedule a project from Completion Date:
-
Click the Main Menu icon
-
°ä±ô¾±³¦°ìÌý New Project, then select New Project from the drop-down that appears.
For more information about creating projects, see the article Create a project.
-
Select Project Details in the left panel.
-
Click the Edit Project icon
-
In the Project dates section, click the Schedule Mode field, then select Completion Date.
-
Specify the Planned Completion Date of the project.
-
Click Save Changes.
As you start adding tasks to your project, the Planned Start Date of the project calculates based on the total Duration of all of the tasks.
Automatically set the Planned Completion Date of a project
The Planned Completion Date of a project is automatically calculated by Workfront when you schedule the project from Start Date.
To schedule a project from Start Date:
-
Click the Main Menu icon
-
°ä±ô¾±³¦°ìÌý New Project, then select New Project from the drop-down that appears.
For more information about creating projects, see the article Create a project.
-
Select Project Details in the left panel.
-
Click the Edit Project icon
-
In the Project dates section, click the Schedule Mode field, then select Start Date.
-
Specify the Planned Start Date of the project.
-
Click Save Changes.
As you start adding tasks to your project, the Planned Completion Date of the project calculates based on the total Duration of all of the tasks.
For more information about Task Duration, see the article Overview of Task Duration and Duration Type.
The Planned Completion Date of the project coincides, in this case, with the Planned Completion Date of the last task on the project.